Views:
Before beginning the Generation Interconnection application,  applicants should determine whether their resource is located within MISO territory before identifying a Point of Interconnection (POI). To make this determination, first, please review the Transferred Transmission Facilities listings, which will help you look up valid Points of Interconnection.
 
From these you can evaluate substations as potential POI by using the POI Map (POI Self-Check tool). On this page, you can also review the Queue map.
 
If you have questions, you may also send an Ad Hoc request with a Site Map to GInterconnection@misoenergy.org and we will schedule a call with you and the potential Transmission Owner to identify any issues or confirm your intentions.
 
For more information, please see BPM 015 – Generation Interconnection